Phase III
Timelines:
Summer 2008 * Phase III school setup in eSIS - NWOCA staff
Fall 2008 *
Continued conversion of files from the Legacy System into eSIS.
* Final demographic, course, teacher, room conversions. *
Partial "Go-Live" * Pre-Scheduling training and processing begins.
* Master
Timetable Builder (MTB) training and scheduling process begins.
* Final conversions complete (Remaining McSIS data - COHI, ABHI, etc.) (All EMIS-related data will be converted into eSIS after close of Yearend EMIS reporting)
Fall 2009 * Phase III Districts fully live on eSIS at the start of the 2009/2010 school year!!
Important Note: NWOCA will be using the "Train-the-trainer" approach to training in that we will train a core team of trainers that will then train the remaining staff in your district. This was important in phase II, and will be even more critical to the success of phase III as more districts are implemented. NWOCA's staff is limited (8 for entire NWOCA consortium that support EMIS/SIS/eSIS for all of NWOCA's districts), so we are not able to train all staff in all districts while adequately maintaining support levels for districts.
The way we have seen this work best is if a district can identify one or two individuals as the core contacts/trainers who will attend nearly every training. These individuals will also coordinate any trainings in your district. Secondly, when pertanent these core trainers/contacts will bring along one or two staff members to trainings relevant to their position.
Example (Admission/Withdraw training):
- Core trainer/contact - Maybe your EMIS Coordinator or Tech. Coordinator - Additional Attendee - one or two strong secretaries or admissions clerks that handle that function in the district. - Post-training - Core contact + additional attendee (Admission clerk) setup and run trainings within district to train additional staff needing to learn this functionality in eSIS. |